All Bicycle & Pedestrian Projects

Bascom Complete Street Improvements (Hamilton to I-880)

Category: Bicycle & Pedestrian: Capital Projects
Grantee: VTA
Total Expenditures:$6,075,172
Total Audited Expenditures:$5,021,607
Total Unaudited Expenditures*:$1,053,565
* Unaudited Expenditures become an Audited Expenditure once the annual audit is completed.
Fiscal YearAllocationsAwardsAudited Expenditures
2021$6,843,533$6,843,533∅
2022∅∅$143,709
2023∅∅$1,142,185
2024∅∅$2,422,022
2025∅∅$1,313,691
Total$6,843,533$6,843,533$5,021,607
Discrepancies may occur due to the use of rounding.
Last Modified: October 28th 2026, 8:38 pm