All Highway Interchanges Projects

Double Lane Southbound US101 off-ramp to Southbound SR87

Category: Highway Interchanges
Grantee: VTA
Total Expenditures:$2,993,348
Total Audited Expenditures:$3,011,266
Total Unaudited Expenditures*:$-17,917
* Unaudited Expenditures become an Audited Expenditure once the annual audit is completed.
Fiscal YearAllocationsAwardsAudited Expenditures
2018$1,500,000
2019$1,500,000
2020$1,000,000$1,000,000$80,901
2021$500,000$500,000$167,206
2022$1,747,720
2023$737,149
2024$270,730
2025$7,560
Total$3,000,000$3,000,000$3,011,266
Discrepancies may occur due to the use of rounding.