Highway Program Management Oversight
Provide program management & oversight for Highway Interchange program.
Category: Highway Interchanges
Grantee: VTA | Total Expenditures: | $263,597 |
| Total Audited Expenditures: | $178,657 |
| Total Unaudited Expenditures*: | $84,940 |
* Unaudited Expenditures become an Audited Expenditure once the annual audit is completed.
| Fiscal Year | Allocations | Awards | Audited Expenditures |
|---|
| 2020 | $400,000 | $400,000 | $16,228 |
| 2021 | ∅ | ∅ | $32,810 |
| 2022 | ∅ | ∅ | $71,068 |
| 2023 | ∅ | ∅ | $31,884 |
| 2024 | ∅ | ∅ | $26,668 |
| Total | $400,000 | $400,000 | $178,657 |
|---|
Discrepancies may occur due to the use of rounding.
Related Documents: None
Last Modified: February 4th 2026, 6:47 pm