All Highway Interchanges Projects

US 101/Trimble/De La Cruz Interchange Improvements

Category: Highway Interchanges
Grantee: VTA
Total Expenditures:$45,438,870
Total Audited Expenditures:$44,234,778
Total Unaudited Expenditures*:$1,204,091
* Unaudited Expenditures become an Audited Expenditure once the annual audit is completed.
Fiscal YearAllocationsAwardsAudited Expenditures
2018$4,000,000∅∅
2019∅$4,000,000∅
2020$35,000,000∅$2,937,581
2021$8,000,000∅$1,811,274
2022∅∅$14,441,621
2023∅∅$11,128,550
2024$550,000$43,550,000$8,482,048
2025∅∅$5,433,704
Total$47,550,000$47,550,000$44,234,778
Discrepancies may occur due to the use of rounding.
Last Modified: October 28th 2026, 8:38 pm