All Highway Interchanges Projects

US 101/Zanker Rd/Skyport Dr/N 4th St Interchange

Category: Highway Interchanges
Grantee: VTA
Total Expenditures:$4,928,037
Total Audited Expenditures:$4,538,564
Total Unaudited Expenditures*:$389,473
* Unaudited Expenditures become an Audited Expenditure once the annual audit is completed.
Fiscal YearAllocationsAwardsAudited Expenditures
2018$3,000,000
2019$3,000,000
2020$6,000,000$6,000,000
2021$149,634
2022$1,931,242
2023$1,012,087
2024$904,007
2025$9,470,000$541,595
Total$18,470,000$9,000,000$4,538,564
Discrepancies may occur due to the use of rounding.
Last Modified: May 27th 2026, 12:27 am